Line 9 of the Mexico City Metro
From Tacubaya to Pantitlán in 12 stations: eight underground and four elevated in the east, from Velódromo to Pantitlán.
About Line 9
Twelve stations and 13.0 km in service (15.7 km with the maneuvering tracks) between TacubayaES, in Miguel Hidalgo, and Pantitlán, on the boundary of Venustiano Carranza and Iztacalco. From Tacubaya to Mixiuhca it runs underground; Velódromo, Ciudad Deportiva, Puebla and Pantitlán sit on an elevated viaduct.
It has five interchanges: Tacubaya (lines 1 and 7), Centro Médico (3), ChabacanoES (2 and 8), Jamaica (4) and Pantitlán (1, 5 and A). In 2024 the operator recorded 80.6 million entries at its stations; that figure is not for a full year, because Ciudad Deportiva, Puebla and Pantitlán were closed from January to June for works on the elevated stretch. The SEMOVI GTFS estimates about 24 minutes end to end.
Stations on Line 9
12 stations in the order the operator publishes them, 5 of them interchanges with another line (marked with a ring and the colors of the other lines).
Hours and frequency on Line 9
| Day | Network service hours |
|---|---|
| Monday to Friday | 5:00 to 24:00 |
| Saturday | 6:00 to 24:00 |
| Sundays and public holidays | 7:00 to 24:00 |
These are the service hours the operator publishes for the whole network, the same at every station. It does not publish a first and last train time for each station: a train leaving a terminus at opening time takes a few minutes to reach the others, and service can change on special days.
| Line | Headway, monday to friday | Headway, saturday | Headway, sundays and public holidays |
|---|---|---|---|
| L9 | every 3 min | every 3 min | every 3 min |
An estimate: it is the single headway the SEMOVI GTFS models for the whole line and the whole day (open data, valid until December 31, 2025). The operator does not publish headways by time of day; at peak and off-peak times the real interval changes.
Opened section by section
| Date | Section | Stations |
|---|---|---|
| August 26, 1987 | Pantitlán – Centro Médico | 9 |
| August 29, 1988 | Centro Médico – Tacubaya | 3 |
Sections and dates from the line page the operator publishes, in the order it publishes them.
The busiest stations on Line 9
| # | Station | Entries in 2024 (this line) |
|---|---|---|
| 1 | TacubayaES | 21,125,323 |
| 2 | VelódromoES | 12,793,922 |
| 3 | ChilpancingoES | 12,757,437 |
| 4 | MixiuhcaES | 7,413,757 |
| 5 | PatriotismoES | 5,741,128 |
Station ridership by line for 2024 as published by the operator (recorded entries). At interchanges only the share belonging to this line is counted.
History
Line 9 opened on August 26, 1987 with nine stations between Centro Médico and Pantitlán. The plan allowed for a tenth, “Asturias”, between Jamaica and Chabacano, dropped after local opposition. On August 29, 1988 the western extension opened, with three stations as far as Tacubaya. The original plan was to reach Observatorio; the project was made official on May 27, 2017 and its studies were put out to tender, but the works were never tendered.
The elevated stretch has closed twice to correct the sinking of its columns. From March 27, 2021 until April 7, earlier than planned, Pantitlán, Puebla and Ciudad Deportiva closed, with Velódromo as a temporary terminus, to remove track, guide bars and ballast, level the track and correct the profile of the box girder. In December 2023 a differential subsidence of about 80 centimetres was found, and from December 17 Pantitlán, Puebla and Ciudad Deportiva closed to relevel the track and replace the concrete beams. Full service returned on September 10, 2024, after almost nine months.
How the service works
Line 9 runs on rubber-tired trains. The hours the operator publishes are those of the whole network: 5:00 to 24:00 Monday to Friday, 6:00 to 24:00 on Saturdays and 7:00 to 24:00 on Sundays. Those are the service hours of the whole network, the same at every station; the operator does not publish times at which trains call. The SEMOVI GTFS models a train every 3 minutes, an estimate. As of October 20, 2026 we had no record of long closures; the last long one was on the elevated stretch, from December 17, 2023 to September 10, 2024. You can find it on the Metro map.
The trains
It opened in 1987 with MP-68 trains that came from Line 1. In 1996 the operator assigned it 26 trains refurbished by Bombardier Transportation México to the MP-68R93 standard. In mid-2008 NC-82 trains arrived from Line 5, and in the 2010s and in 2019 NM-83Bs came from Line 1, which the arrival of the NM-16s had freed up.
Frequently asked questions
In December 2023 a differential subsidence of about 80 centimetres was found. From December 17 Pantitlán, Puebla and Ciudad Deportiva closed to relevel the track and replace the concrete beams. The reopening was announced for May 2024 but was put back to September 10, 2024.
No. The original plan was to extend it to Observatorio, and on May 27, 2017 the project was made official, with a tender for studies in August of that year. The works were never tendered and the line still ends at Tacubaya.
The original plan included a station called “Asturias” between Jamaica and Chabacano. It was dropped after local opposition, and the line opened in 1987 with nine stations instead of ten.