--:-- · Mexico City

Line 7 of the Mexico City Metro

From El Rosario to Barranca del Muerto through the west of the city: the deepest line on the network, with 14 stations.

About Line 7

Stations
144 with an interchange
Route
El Rosario – Barranca del Muerto
Length
17.01 kmin service; 18.78 km in all including the maneuvering tracks, according to the operator
Opened
1984December 20, 1984
Wheels
Rubber-tiredtrains on rubber tires
Ridership 2024
85.6 millionentries at its stations, as counted by the operator

Fourteen stations and 17.0 km in service (18.8 km with the maneuvering tracks) between El RosarioES, in Azcapotzalco, and Barranca del MuertoES, on the boundary of Benito Juárez and Álvaro Obregón. Apart from El Rosario, all of them are underground. In between it crosses Miguel Hidalgo by way of Tacuba, Polanco, Auditorio and Constituyentes.

It has four interchanges: El Rosario (Line 6), Tacuba (2), TacubayaES (1 and 9) and Mixcoac (Line 12). Because it was built through hilly ground, it is the deepest line on the network: it reaches 40 metres below the surface at Camarones. In 2024 the operator recorded 85.6 million entries at its stations, and the SEMOVI GTFS estimates about 28 minutes end to end.

Stations on Line 7

14 stations in the order the operator publishes them, 4 of them interchanges with another line (marked with a ring and the colors of the other lines).

Hours and frequency on Line 7

DayNetwork service hours
Monday to Friday5:00 to 24:00
Saturday6:00 to 24:00
Sundays and public holidays7:00 to 24:00

These are the service hours the operator publishes for the whole network, the same at every station. It does not publish a first and last train time for each station: a train leaving a terminus at opening time takes a few minutes to reach the others, and service can change on special days.

LineHeadway, monday to fridayHeadway, saturdayHeadway, sundays and public holidays
L7every 4 minevery 4 minevery 4 min

An estimate: it is the single headway the SEMOVI GTFS models for the whole line and the whole day (open data, valid until December 31, 2025). The operator does not publish headways by time of day; at peak and off-peak times the real interval changes.

Opened section by section

DateSectionStations
December 20, 1984Tacuba – Auditorio4
August 22, 1985Auditorio – Tacubaya2
December 19, 1985Tacubaya – Barranca del Muerto2
November 29, 1988Tacuba – El Rosario4

Sections and dates from the line page the operator publishes, in the order it publishes them.

The busiest stations on Line 7

#StationEntries in 2024 (this line)
1Polanco11,803,141
2Auditorio11,636,000
3Barranca del MuertoES11,103,749
4El RosarioES9,389,267
5San JoaquínES7,577,938

Station ridership by line for 2024 as published by the operator (recorded entries). At interchanges only the share belonging to this line is counted.

History

Its tunnels were dug by the Austrian method: a roadheader opens the tunnel, concrete is sprayed onto the walls as a first lining and hydraulic concrete is then placed as the permanent wall. The open-face shield method was also used, in which hydraulic jacks around the shield push the excavation forward and the ground is lined with concrete segments. The work was given to Grupo ICA.

The first stretch, Tacuba–Auditorio, opened on December 20, 1984 with four stations and 5.4 km. On August 22, 1985 Constituyentes and Tacubaya followed, and on December 19 of that same year the line reached Barranca del Muerto, its southern terminus. The northern extension opened on November 29, 1988, with four stations from Tacuba to El Rosario, which became the northern terminus. That extension completed the line: 14 stations and 18.8 km of track, counting the maneuvering tracks.

How the service works

Line 7 runs on rubber-tired trains. The service hours are the same across the network: 5:00 to 24:00 Monday to Friday, 6:00 to 24:00 on Saturdays and 7:00 to 24:00 on Sundays. Those are the service hours of the whole network, the same at every station; the operator does not publish times at which trains call. The SEMOVI GTFS models a train every 4 minutes, an estimate and not a figure from the operator. As of October 20, 2026 we had no record of long closures on the line. The Metro map shows where it meets the rest of the network.

The trains

When it opened in 1984 it received MP-68, NM-73A and NM-79 trains from other lines. In 1999 the operator assigned it 28 MP-68R96B trains refurbished by Bombardier Transportation México. In the 2000s NM-02 trains arrived from Line 2 and the NM-73As and NM-73Bs were refurbished. Between 2007 and 2011 MP-68R93, NM-73B, NM-79 and NM-83A trains ran on it.

Frequently asked questions

It is the deepest on the whole network because it was built through hilly ground. At Camarones it reaches 40 metres below the surface.

With two techniques: the Austrian method, with a roadheader and a two-layer concrete lining, and the open-face shield, which advances with hydraulic jacks and lines the tunnel with concrete segments. The work was done by Grupo ICA.

First the Tacuba–Auditorio stretch, on December 20, 1984. Then came Constituyentes and Tacubaya on August 22, 1985, the stretch to Barranca del Muerto on December 19, 1985 and, on November 29, 1988, the four stations from Tacuba to El Rosario.